Electrical Panel (Service Capacity)

Your home's circuit-breaker box and the amperage of its main service — the hidden line item in heat pump retrofits. The main breaker's number (60, 100, 125, 200) is your service size; a heat pump needs a dedicated 240-volt circuit with real headroom.

The longer answer

Whether a panel can take a heat pump is arithmetic, not opinion: an NEC load calculation tallies what's connected against what the service supplies. Equipment choice moves the answer too — ductless systems and right-sized variable-speed units draw far less than oversized ducted setups with big strip backup, and modern load-management devices let large loads share capacity.

The failure mode to avoid is the change-order ambush: a bid that never asked about the panel 'discovering' it mid-install. Any heat pump bid on a pre-1980 home should answer the panel question at estimate time, priced.

The Seattle angle

Pre-war Seattle homes commonly carry 60–100 amp service. Sometimes capacity exists; sometimes a panel upgrade joins the electrification project — regional guidance often lands full electrification at 150–200 amps.

Request Service

Ready for comfort you can count on?

Whether it's a furnace that quit on a cold morning or a whole new system, the Glendale team is ready. Honest pricing, expert work, and 87+ years behind every visit.

Hours & Emergency

  • Mon–Sat: 8:00 AM – 7:00 PM
  • Sun: Emergency On-Call Only
  • Emergency line: (206) 243-7700